Eldridge Gonaway

DESCRIPTION

Interior and exterior rehab of a 40-unit affordable housing complex in seven separate freestanding buildings. Interior work included new bathrooms, kitchens, interior finishes, unit subpanels and main feeders. Exterior work included complete exterior finishes (converting existing stucco building to new cement board siding with added plywood sheathing), extension of roof eaves, installation of moment frames and Simpson Strong Walls for seismic upgrade, landscaping, and additions to the community room. Earlier phases of the project included furnace and water replacement throughout and lighting upgrades.

ARCHITECT

Struthers Dias Architects
http://struthersdias.com/
Contact: Theresa Dias
(510) 924-0377

OWNER/PROJECT MANAGER

Resources for Community Development
Contact: Lauren Brewer
(510) 734-4412

COST

$8,319,631

COMPLETION DATE

August 2014
Eldridge Gonaway project